0

Civil Engineering Drawing Mcqs

Q:

Which among the following is not a principle of planning?

A) Furniture requirements B) Aspect
C) Prospect D) Respect
 
Answer & Explanation Answer: D) Respect

Explanation: *Aspect- Is meant for arrangement of doors and windows 1n the external walls of the bui1iding wh1ch allows the natural gifts of sun shine and air, scenery etc.
*Prospect- is determine by the views desired from certain rooms of the house and is interest by surroundings peculiarities of selected site
*Furniture requirements- it 1s the functional requirement of a room decides the required furniture.

View Answer Discuss

448
Q:

For a cone, the front view will be a ___________ with the slant edge showing the true length of the generator of the cone.

A) Square B) Rectangle
C) Triangle D) Circle
 
Answer & Explanation Answer: C) Triangle

Explanation: Not available for this question

View Answer Discuss

436
Q:

Which is corresponded to zoom mouse wheel?

A) Extend/all B) Zoom in/ Zoom out
C) Pan and scan D) Scale
 
Answer & Explanation Answer: B) Zoom in/ Zoom out

Explanation: To use the Zoom command’s Window option, you click one corner, release the mouse button, and then click the other corner. Realtime: Enables you to zoom in and out by starting a realtime zoom and then dragging the magnifying-glass cursor up (to zoom in) or down (to zoom out).

View Answer Discuss

383
Q:

Auxiliary views cannot be used for the determining _____________

A) the true length of a line B) the point-view of a line
C) the edge-view of a line D) the apparent size
 
Answer & Explanation Answer: D) the apparent size

Explanation: Not available for this question

View Answer Discuss

268
Q:

The estimate which prepared using any rough method to get the approximate cost construction anticipated in a project is called an ______________ estimate.

A) approximate B) precise
C) exact D) rough
 
Answer & Explanation Answer: A) approximate

Explanation: The approximate estimate is done in order to find out an approximate cost in very short time before starting the project. The estimation is made before selecting the final specification and design of the project. This method is also known as preliminary or rough estimate.

View Answer Discuss

243
Q:

The development of cylinder is a _______

A) triangle B) rectangle
C) square D) trapezium
 
Answer & Explanation Answer: B) rectangle

Explanation: Not available for this question

View Answer Discuss

224
Q:

The length to height ratio of a closed filled arrow head is?

A) 1:3 B) 3:1
C) 1:2 D) 2:1
 
Answer & Explanation Answer: B) 3:1

Explanation: Not available for this question

View Answer Discuss

222
Q:

A building costing Rs.700000.00 has been constructed on a freehold land measuring 100 sq m recently in a big city. Prevailing rate of land in the neighbourhood is Rs.150.00 per sq m. Determine the net rent of the property, if the expenditure on an outgoing including sinking fund is Rs.24000.00 per annum. Work out also the gross rent of the property per month.

A) 48000/-, 8000/- B) 18000/-, 6000/-
C) 46700/-, 6000/- D) 48000/-, 6000/-
 
Answer & Explanation Answer: D) 48000/-, 6000/-

Explanation: Cost of construction = Rs.700000.00
Cost of land @Rs.150.00 per sq m = 100*150 = Rs.150000.00
Net return:
On building @ 6% on the cost of construction = 700000.00 *6/100 = Rs.42000.00
On the land @ 4% on the cost of land = 700000.00 *6/100 = Rs.6000.00
Total net rent per year = Rs.48000.00
Gross rent = Net rent + outgoings = 48000+24000.00 = 72000.00 per annum
Gross rent per month = 72000/12 = 6000.00.

View Answer Discuss

221